Project Update: August 8, 2024
The District of Tofino is pleased to announce significant progress on the Mackenzie Beach Road Upgrades project.
As of August 1, 2024, paving and line painting have been completed, marking a key milestone in the project. The majority of the roadworks and upgrades to the drainage conveyance systems are now finished, with only a few minor items remaining.
Completed Works:
• Stormwater drainage conveyance (culverts and pipe, storm manhole, headwalls)
• Grading and road widening
• Sidewalks and curb at the turn-around area
• Paving and line painting
Remaining Work:
• Wheel stops
• Traffic signage (one-way, parking, and formalized speed)
• Bollards at highway crossing and miscellaneous barriers at the turn-around loop
• Wayfinding signage at the loop
• Landscaping at the loop
This week, the contractor will continue installing bollards and traffic signage along the roadway.
Parallel Project - Mackenzie Beach Washroom Project:
In parallel with the road upgrades, work will soon begin on the Mackenzie Beach Washroom Project. The remaining items for this project include:
• Installation of a hydro pole for washroom electrical
• Construction of the washroom concrete pad and building
The District appreciates the community’s patience and cooperation throughout the construction of these essential upgrades.
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends