Project Update: August 8, 2024
![](https://s3.ca-central-1.amazonaws.com/ehq-production-canada/f81e9592f7e93d2e75c32ca073767f7e6a8a9f26/original/1723134845/5d2d862e869918cf68787b854a250bed_mbr3.jpg?1723134845)
The District of Tofino is pleased to announce significant progress on the Mackenzie Beach Road Upgrades project.
As of August 1, 2024, paving and line painting have been completed, marking a key milestone in the project. The majority of the roadworks and upgrades to the drainage conveyance systems are now finished, with only a few minor items remaining.
Completed Works:
• Stormwater drainage conveyance (culverts and pipe, storm manhole, headwalls)
• Grading and road widening
• Sidewalks and curb at the turn-around area
• Paving and line painting
Remaining Work:
• Wheel stops
• Traffic signage (one-way, parking, and formalized speed)
• Bollards at highway crossing and miscellaneous barriers at the turn-around loop
• Wayfinding signage at the loop
• Landscaping at the loop
This week, the contractor will continue installing bollards and traffic signage along the roadway.
Parallel Project - Mackenzie Beach Washroom Project:
In parallel with the road upgrades, work will soon begin on the Mackenzie Beach Washroom Project. The remaining items for this project include:
• Installation of a hydro pole for washroom electrical
• Construction of the washroom concrete pad and building
The District appreciates the community’s patience and cooperation throughout the construction of these essential upgrades.