Year End for 2022
Happy Holidays! - Crews will be observing a pause in construction throughout the week of December 26, 2022 and will be resuming construction on January 2023.
The majority of rock blasting has been completed at the Facility location and crews have cast the first structural concrete onsite for the Mechanical Building sump pit, walls and slab!
Early 2023 crews will be mobilizing throughout the District to commence work on modifying Tofino's sewage collection system and working towards casting the base slab for the Mechanical Building.
Thank you for your contribution!