Summer 2023 Update

As of June 26, 2023, construction on the Wastewater Treatment Plant continues to make progress

  • Steel EQ, IFAS and Secondary clarifier tanks are almost fully erected on site
  • Mechanical building and Headworks Build steel Mezzanines are erected
  • Process pipe racking and process piping currently being installed – continuous
  • Warren Way pump station concrete base slab ready for pour
  • Cedar St outfall clearing, grubbing and site prep
  • Fusing and prepping outfall pipe at Berryman Point – ongoing
  • Barging outfall pipe and beginning outfall install July 3rd