Summer 2023 Update
As of June 26, 2023, construction on the Wastewater Treatment Plant continues to make progress
- Steel EQ, IFAS and Secondary clarifier tanks are almost fully erected on site
- Mechanical building and Headworks Build steel Mezzanines are erected
- Process pipe racking and process piping currently being installed – continuous
- Warren Way pump station concrete base slab ready for pour
- Cedar St outfall clearing, grubbing and site prep
- Fusing and prepping outfall pipe at Berryman Point – ongoing
- Barging outfall pipe and beginning outfall install July 3rd
1st Street Pump Station
Wastewater Treatment Plant, June 2023
Wastewater Treatment Plant, June 2023
