Main Street & First Street Conveyance Work (March - May 2023)

Overview

Construction will be affecting sections of Main Street & First Street from March through May of 2023 as part of the Wastewater Treatment Plant Project. Main Street will be limited to one way vehicle traffic through May 2023. Access will remain open to all properties and businesses during this time. Please see below for further details of the traffic disruptions:


March 20 - April 8, 2023

Main Street will be limited to one-way vehicle traffic from Second Street to Third Street during this period. See graphic below.

  • Access to Method Marine will still be accessible by vehicle
  • Businesses and properties on both sides of Main Street will still be accessible to pedestrians
  • Bicyclists must dismount and walk, using the pedestrian corridors
  • Pump station work to be completed in May
  • Please note that further Main St conveyance work will begin west of Second St on April 3rd limiting the intersection to one way traffic as per the second graphic.



April 3 - 14, 2023

Main Street will be limited to one-way vehicle traffic from 331 Main Street (The Legion) to Second Street during this period. See graphic below.

  • Wharf Street and Second Street will remain open to 2 way traffic
  • Businesses and properties on both sides of Main Street will still be accessible to pedestrians
  • Bicyclists must dismount and walk, using the pedestrian corridors



April 17 - May 5, 2023

First Street will be limited to single lane alternating vehicle traffic from Main Street to First Street Dock during this period. See graphic below.

  • Flaggers will be present on First Street 7AM - 7PM weekdays to direct single lane alternating vehicle traffic
  • At the end of each workday, crews will clear up the work site and re-open First Street to regular two-way traffic overnight (7PM - 7AM).
  • Vehicle access to Savary Island Pie Company and Grice Park Kayak Launch will be reduced to single lane alternating traffic 7AM - 7PM each work day as well.
  • Work day hours (7AM - 7PM) may vary day-by-day.
  • Businesses and properties on both sides of First Street will still be accessible to pedestrians
  • Bicyclists must dismount and walk, using the pedestrian corridors
  • Pump station work to be completed in May


Share Main Street & First Street Conveyance Work (March - May 2023) on Facebook Share Main Street & First Street Conveyance Work (March - May 2023) on Twitter Share Main Street & First Street Conveyance Work (March - May 2023) on Linkedin Email Main Street & First Street Conveyance Work (March - May 2023) link