The Cox Bay Maltby Washroom is a key infrastructure project identified in the 2022-2024 Resort Development Strategy. The project is intended to provide beachgoers with access to a washroom and change room facility at one of Tofino’s most popular public beach accesses. The full cost of this project is funded by the Province's Resort Municipality Initiative (RMI).

Currently, the presence of a single stall washroom, a fair distance from parking areas, falls short of meeting the needs of both residents and visitors at this popular location. Additional parking has been added in recent years, and beach pay parking was implemented

The Cox Bay Maltby Washroom is a key infrastructure project identified in the 2022-2024 Resort Development Strategy. The project is intended to provide beachgoers with access to a washroom and change room facility at one of Tofino’s most popular public beach accesses. The full cost of this project is funded by the Province's Resort Municipality Initiative (RMI).

Currently, the presence of a single stall washroom, a fair distance from parking areas, falls short of meeting the needs of both residents and visitors at this popular location. Additional parking has been added in recent years, and beach pay parking was implemented in 2020. The new washroom facility will compliment, and not replace, the existing single stall washroom, located close to the beach.

The proposed new washroom facility was initially designed and tendered in late 2021, however due to market conditions at that time, pricing received was well in excess of the District’s budget for the project and tenders rejected.

Reducing or changing the scope of the washroom facility was explored, however a resulting smaller facility would not be sufficient to support the number of users at this location and alternative, lower cost materials would not provide the community with a durable, low maintenance facility to last for decades.

  • Project Update: June 3, 2024

    Share Project Update: June 3, 2024 on Facebook Share Project Update: June 3, 2024 on Twitter Share Project Update: June 3, 2024 on Linkedin Email Project Update: June 3, 2024 link

    The District of Tofino is pleased to announce that the construction of the Cox Bay/Maltby Washroom is now complete and will be available for public use as of Tuesday, June 4, 2024.

    This new facility at one of Tofino's popular beaches will now provide beachgoers with multiple change rooms, washrooms, outdoor showers, and water fountains.

    The full cost of this project was funded by the Province of British Columbia's Resort Municipality Initiative (RMI).

  • Project Update: May 10, 2024

    Share Project Update: May 10, 2024 on Facebook Share Project Update: May 10, 2024 on Twitter Share Project Update: May 10, 2024 on Linkedin Email Project Update: May 10, 2024 link
    supporting image

    The Cox Bay/Maltby Washroom project is nearing completion. The washrooms are expected to be open and operational by the end of May 2024.

  • Project Update: February 26, 2024

    Share Project Update: February 26, 2024 on Facebook Share Project Update: February 26, 2024 on Twitter Share Project Update: February 26, 2024 on Linkedin Email Project Update: February 26, 2024 link
    supporting image

    The District of Tofino is making significant progress on the Cox Bay/Maltby Washroom project, aiming for completion by the end of May 2024.

    Currently, the construction area is fully fenced off. During construction, it is important to observe signage and refrain from entering the construction site.

  • Project Breaks Ground October 4, 2023

    Share Project Breaks Ground October 4, 2023 on Facebook Share Project Breaks Ground October 4, 2023 on Twitter Share Project Breaks Ground October 4, 2023 on Linkedin Email Project Breaks Ground October 4, 2023 link

    Construction will begin on October 4, 2023 with site preparation in the Maltby Parking Lot on Braiden Way, South of the Pay Parking Kiosk. Parking and traffic may be disrupted. Thank you for your patience as we develop these key amenities that will benefit residents and visitors.

Page last updated: 03 Jun 2024, 03:42 PM